Filters
Question type

Study Flashcards

The specifications for a product are 6 mm ± 0.1 mm. The process is known to operate at a mean of 6.05 with a standard deviation of 0.01 mm. What is the Cpk for this process?


A) 3.33
B) 1.67
C) 5.00
D) 2.50
E) 1.33

F) B) and D)
G) B) and E)

Correct Answer

verifed

verified

Patterns of data on a control chart suggest that the process may have nonrandom variation.

A) True
B) False

Correct Answer

verifed

verified

A quality analyst wants to construct a control chart for determining whether four machines, all producing the same product, are under control with regard to a particular quality attribute. Accordingly, she inspected 1,000 units of output from each machine in random samples, with the following results:  Machine  Total Defectives #123#215#329#413\begin{array} { l c } \text { Machine } & \text { Total Defectives } \\\hline \# 1 & 23 \\\# 2 & 15 \\\# 3 & 29 \\\# 4 & 13\end{array} What is the estimate of the standard deviation of the sampling distribution of sample proportions for whenever this process is under control?


A) .016
B) .00016
C) .04
D) .0044
E) .00002

F) A) and E)
G) B) and C)

Correct Answer

verifed

verified

A quality analyst wants to construct a sample mean chart for controlling a packaging process. He knows from past experience that whenever this process is under control, package weight is normally distributed with a mean of 20 ounces and a standard deviation of two ounces. Each day last week, he randomly selected four packages and weighed each:  Weight (ounces)   Day  Monday 23222324 Tuesday 23211921 Wednesday 20192021 Thursday 18192019 Friday 18202220\begin{array} { r } { \text { Weight (ounces) } }\\\begin{array} { l l l l l } \text { Day } \\\hline \text { Monday } & 23 & 22 & 23 & 24 \\\text { Tuesday } & 23 & 21 & 19 & 21 \\\text { Wednesday } & 20 & 19 & 20 & 21 \\\text { Thursday } & 18 & 19 & 20 & 19 \\\text { Friday } & 18 & 20 & 22 & 20\end{array}\end{array} If he uses upper and lower control limits of 22 and 18 ounces, what is his risk (alpha) of concluding this process is out of control when it is actually in control (Type I error) ?


A) 0.0026
B) 0.0456
C) 0.3174
D) 0.6826
E) 0.9544

F) B) and E)
G) A) and C)

Correct Answer

verifed

verified

The basis for a statistical process control chart is a(the) :


A) process capability.
B) sampling distribution.
C) control limit.
D) sample range.
E) sample mean.

F) B) and C)
G) A) and D)

Correct Answer

verifed

verified

A c-chart is used to monitor the number of defects per unit for process output.

A) True
B) False

Correct Answer

verifed

verified

The optimum level of inspection minimizes the sum of inspection costs and the cost of passing defectives.

A) True
B) False

Correct Answer

verifed

verified

An operator collected the following time series data from a process: 4.04.44.34.54.64.24.14.5\begin{array} { l l l l l l l l } 4.0 & 4.4 & 4.3 & 4.5 & 4.6 & 4.2 & 4.1 & 4.5\end{array} (A) Determine the number of A/B runs. (B) Determine the number of up/down runs.

Correct Answer

verifed

verified

There are six above-...

View Answer

The chair of the operations management department at Quality University wants to construct a p-chart for determining whether the four faculty teaching the basic P/OM course are under control with regard to the number of students who fail the course. Accordingly, he sampled 100 final grades from last year for each instructor, with the following results:  Instructor  Number of Failures  Prof. A 13 Prof. B 0 Prof. C 11 Prof. D 16\begin{array} { l c } \text { Instructor } & \text { Number of Failures } \\\hline \text { Prof. A } & 13 \\\text { Prof. B } & 0 \\\text { Prof. C } & 11 \\\text { Prof. D } & 16\end{array} What are the .95 (5 percent risk of Type I error) upper and lower control limits for the p-chart?


A) .95 and .05
B) .13 and .07
C) .1588 and .0412
D) .16 and .04
E) .1774 and .0226

F) B) and D)
G) A) and B)

Correct Answer

verifed

verified

Consider the following information:  Observations 123456 Num. of defects 10181315912\begin{array} { l r r r r r r } \text { Observations } & 1 & 2 & 3 & 4 & 5 & 6 \\\hline \text { Num. of defects } & 10 & 18 & 13 & 15 & 9 & 12\end{array} The number of runs up and down for the preceding data is:


A) 3.
B) 4.
C) 5.
D) 6.
E) none of these.

F) B) and D)
G) A) and E)

Correct Answer

verifed

verified

A shift in the process mean for a measured characteristic would most likely be detected by a:


A) p-chart.
B) x-bar chart.
C) c-chart.
D) R-chart.
E) s-chart.

F) A) and E)
G) B) and C)

Correct Answer

verifed

verified

A stent for use in coronary surgery requires a special coating. Specifications for this coating call for it to be at least 0.05 millimeters but no more than 0.15 millimeters. If, when the coating process is in control, the long-run average is 0.09 millimeters, what metric would be used to assess this process's capability?

Correct Answer

verifed

verified

A quality analyst wants to construct a control chart for determining whether three machines, all producing the same product, are under control with regard to a particular quality variable. Accordingly, he sampled four units of output from each machine, with the following results:  Measurements  Machine #117151517#216251825#323242322\begin{array} {r } { \text { Measurements } } \\\begin{array} { l l l l l } \text { Machine } & \\\hline \# 1 & 17 & 15 & 15 & 17 \\\# 2 & 16 & 25 & 18 & 25 \\\# 3 & 23 & 24 & 23 & 22\end{array}\end{array} What is the sample mean for machine #1?


A) 15
B) 16
C) 17
D) 21
E) 23

F) A) and E)
G) C) and E)

Correct Answer

verifed

verified

Approving the effort that occurs during the production process is known as acceptance sampling.

A) True
B) False

Correct Answer

verifed

verified

Statistical process control focuses on the acceptability of process output.

A) True
B) False

Correct Answer

verifed

verified

A quality analyst wants to construct a control chart for determining whether four machines, all producing the same product, are under control with regard to a particular quality attribute. Accordingly, she inspected 1,000 units of output from each machine in random samples, with the following results:  Machine  Total Defectives #123#215#329#413\begin{array} { l c } \text { Machine } & \text { Total Defectives } \\\hline \# 1 & 23 \\\# 2 & 15 \\\# 3 & 29 \\\# 4 & 13\end{array} For upper and lower control limits of .026 and .014, which machine(s) , if any, appear(s) to be out-of-control for process proportion of defectives?


A) machine #3
B) machine #4
C) machines #3 and #4
D) machines #2 and #3
E) none of the machines

F) A) and E)
G) C) and D)

Correct Answer

verifed

verified

A design engineer wants to construct a sample mean chart for controlling the service life of a halogen headlamp his company produces. He knows from numerous previous samples that this service life is normally distributed with a mean of 500 hours and a standard deviation of 20 hours. On three recent production batches, he tested service life on random samples of four headlamps, with these results:  Service Life (hours)   Sample 149550050550025255155055153470480460470\begin{array} { r } { \text { Service Life (hours) } }\\\begin{array} { l l l l l } \text { Sample } & \\\hline 1 & 495 & 500 & 505 & 500 \\2 & 525 & 515 & 505 & 515 \\3 & 470 & 480 & 460 & 470\end{array}\end{array} What is the standard deviation of the sampling distribution of sample means for whenever service life is in control?


A) 5 hours
B) 6.67 hours
C) 10 hours
D) 11.55 hours
E) 20 hours

F) A) and B)
G) C) and D)

Correct Answer

verifed

verified

A quality analyst wants to construct a control chart for determining whether four machines, all producing the same product, are under control with regard to a particular quality attribute. Accordingly, she inspected 1,000 units of output from each machine in random samples, with the following results:  Machine  Total Defectives #123#215#329#413\begin{array} { l c } \text { Machine } & \text { Total Defectives } \\\hline \# 1 & 23 \\\# 2 & 15 \\\# 3 & 29 \\\# 4 & 13\end{array} What are the control chart upper and lower control limits for an alpha risk of .05?


A) .0272 and .0128
B) .0287 and .0113
C) .029 and .013
D) .0303 and .0097
E) .0332 and .0068

F) B) and C)
G) A) and B)

Correct Answer

verifed

verified

Acceptance sampling, when it is used, is used: (I) before production. (II) during production. (III) after production.


A) I only
B) I and III only
C) I and II only
D) II and III only
E) I, II, and III

F) B) and E)
G) C) and D)

Correct Answer

verifed

verified

The output of a process may not conform to specifications even though the process may be statistically "in control."

A) True
B) False

Correct Answer

verifed

verified

Showing 41 - 60 of 141

Related Exams

Show Answer