Filters
Question type

Study Flashcards

What is the standard time (ST) for this task if the employee worked at a twenty-five percent faster pace than is average and an allowance of twenty percent of the workday is used?


A) 80 seconds
B) 96 seconds
C) 100 seconds
D) 120 seconds
E) 125 seconds

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

Standard times derived from a firm's historical data are known as:


A) predetermined times
B) MTM
C) work sampling times
D) judgmental times
E) standard elemental times

F) B) and E)
G) None of the above

Correct Answer

verifed

verified

What is the standard time (ST) for this task if the employee worked at a twenty-five percent faster pace than is average and an allowance of twenty percent of job time is used?


A) 80 seconds
B) 96 seconds
C) 100 seconds
D) 120 seconds
E) 125 seconds

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

What is the normal time (NT) for this task if the employee worked at a twenty-five percent faster pace than average?


A) 80 seconds
B) 96 seconds
C) 100 seconds
D) 120 seconds
E) 125 seconds

F) All of the above
G) A) and E)

Correct Answer

verifed

verified

An analyst has observed 28 work cycles, for which the average cycle time was five minutes and the performance rating was 1.05.Allowances for the department are 25 percent of job time.What standard time is appropriate for this job?

Correct Answer

verifed

verified

A work sampling study is needed that will estimate the percentage of time a postal clerk spends selling stamps as opposed to other duties.Determine the necessary sample size to estimate that proportion with a confidence of 99.74 percent to within 3 percent, for these cases: 1) No information is currently available concerning that proportion. 2) The proportion is probably no more than 15 percent.

Correct Answer

verifed

verified

For a confidence level of 86.64%, what is the maximum error of the estimate for activity A?

Correct Answer

verifed

verified

How many observations should be made if the analyst wants to be 99.74 percent confident that the maximum error in the observed time is two seconds? Assume that the standard deviation of each task time is 4 seconds.


A) 5
B) 6
C) 25
D) 36
E) 49

F) A) and B)
G) A) and E)

Correct Answer

verifed

verified

The methods analysis chart which describes the portions of a work cycle during which an operator and equipment are busy or idle is a:


A) flow process chart
B) worker-machine chart
C) gang process chart
D) simultaneous-motion (SIMO) chart
E) time/efficiency chart

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

How many observations should be made if she wants to be 95.44 percent confident that the maximum error in the observed time is two seconds? Assume that the standard deviation of the task time is 6 seconds.


A) 5
B) 6
C) 30
D) 36
E) 49

F) B) and D)
G) C) and E)

Correct Answer

verifed

verified

No stopwatch is required in a work sampling study.

A) True
B) False

Correct Answer

verifed

verified