A) hidden interaction costs.
B) things going wrong on a project.
C) normal conditions not applying.
D) changes in project scope.
E) the customer not being clear about their expectations.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) top-down
B) analogous
C) bottom-up
D) reference class
E) professional estimation
Correct Answer
verified
True/False
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
Essay
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Multiple Choice
A) Cost and time important
B) Fixed price contract
C) Customer wants details
D) Internal, small project
E) Large scale project involving several subcontractors
Correct Answer
verified
Multiple Choice
A) human nature.
B) political dynamics.
C) difficulty in predicting the future.
D) size of the project.
E) All of these alternatives are correct.
Correct Answer
verified
Multiple Choice
A) mega projects.
B) high risk.
C) white elephants.
D) mega projects or white elephants.
E) None of these alternatives is correct.
Correct Answer
verified
Multiple Choice
A) Only labor
B) Only materials
C) Only equipment
D) Both labor and materials
E) Labor, materials and equipment
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Multiple Choice
A) They are made by someone who uses experience and / or information from someone else to determine overall project cost and duration.
B) They establish low-cost, efficient methods for completing activities.
C) They typically come from the people actually doing the work and who are most knowledgeable about the task at hand.
D) Estimates are made at the work package level and then "rolled up" to determine estimates for major deliverables and for the project itself.
E) They can take place after the project has been planned in detail.
Correct Answer
verified
Multiple Choice
A) Padding estimates
B) Planning horizon
C) Project structure
D) People
E) Organization culture
Correct Answer
verified
Multiple Choice
A) hidden interaction costs.
B) things going wrong on a project.
C) normal conditions not applying.
D) changes in project scope.
E) there is never a good reason to refine estimates.
Correct Answer
verified
Multiple Choice
A) budgeting.
B) predicting.
C) estimating.
D) planning.
E) guesstimating.
Correct Answer
verified
Multiple Choice
A) Adjusting estimates based on individual forecasting abilities
B) Benchmarking and using the experience of other companies
C) Using time and motion studies
D) Creating historical databases of previous projects
E) Establishing an estimating training course for all employees
Correct Answer
verified